Practice · 14 min read ·
Eleven questions before a quote
Scope creep starts in the first email, not the third month.
Scope creep does not explode in month three. It starts in the first email’s “can we also add…”. The questions I ask before writing a quote surface the real project. Sometimes they end the conversation early. Both outcomes are good.
I do not recite the list from memory as a form. I ask where the conversation opens. If an answer is vague, it goes into the quote as an assumption. I do not start without assumption sign-off. One sentence in email is enough: “yes, the assumptions are correct.” That record surprises nobody later.
1. If this is not done, who is hurt, and by which metric?
No metric means the ask becomes “make it modern.” I cannot price that.
2. How will you know success in three months: one number or one event?
Several metrics can exist; I ask them to pick one primary. Otherwise everyone narrates their own success.
3. Who decides; who can veto?
Two sponsors and three “I’ll take a look” people stall work for weeks. I write decision latency into the assumptions.
4. Which systems exist, and which are untouchable?
The untouchable list usually appears in the last week. Learning it early saves the integration estimate.
5. Where does the data live, and who owns it?
Ownerless data becomes an export request nobody will sign.
6. Any security / compliance constraint (ISO, privacy, sector)?
Constraints lengthen discovery. Hiding them produces audit items in delivery week.
7. How much time can the internal team really give?
“As needed” means zero. I pin hours or days.
8. Is the go-live date fixed, or a target?
Fixed date plus open-ended scope is a warranty fight. I make them choose one.
9. Fixed price, or discover first then price?
Foggy scope makes fixed price a gamble. I say that out loud.
10. What are the three must-haves; can the rest be cut?
If the uncuttable list hits ten items, there is no priority yet.
11. Why not build this inside?
Sometimes the answer is “this should be built inside.” Saying that early beats a three-month wrong contract.
Red flags
“Cover everything; we’ll see later.” No single decision-maker. Fixed deadline with open-ended scope. No success metric. Two of these together and I keep the quote deliberately thin or steer to discovery.
How I use them
Not as a form. Short answers land in the sales note. In the quote PDF, assumptions sit in their own box; if the client skips that box, work does not start. When a change request arrives we open that box: did an assumption break, or is this new scope?
These questions are not gentle. They are clear. Clarity protects both calendars. Declining the wrong work is part of delivery quality.