Fixed price, written list
When scope is clear: one number and a payment schedule. When it is not: discover first — do not bury uncertainty in the rate.
Hourly work sometimes looks fair: pay for what it takes. In practice it bills uncertainty to the client and delays the scope conversation. My default is fixed price plus a written list.
What gets written
In scope: screens, integrations, environments. Line by line; there is no “general improvements” row.
Explicitly out of scope: if it is unwritten, everyone assumes it is included. The out list is not gentle; it is clear.
Assumptions: API docs exist, one decision-maker exists, staging access opens in week one. If an assumption breaks, we talk scope.
Payment slices: discovery / midpoint / go-live. One full payment up front strains both sides.
Change path: out-of-scope is discussed first, then priced. No silent adds.
When to discover
If scope is foggy, fixed price is a gamble. A short paid discovery: problem sentence, options, build-vs-buy, rough roadmap. Then the real quote. Stuffing discovery into a “free chat” exhausts both sides. Free chat produces no written assumptions.
Flexibility
Fixed price is not rigidity. The list can change; just not silently. “Can we also add…” wants a new line and a new number. That friction is healthy. It makes creep visible. Frictionless scope becomes a “this was included” fight three months later.
Trust
Weekly demos insure the fixed price. The client sees progress; I flag drift early. No surprise invoice, no surprise scope. A skipped demo week weakens that insurance; if I miss one, the next demo accounts for two weeks.
When hourly fits
A retainer window, open-ended research, or support work inside the client’s own team. Hourly can be more honest there. For new product build, my default stays a fixed list.
Do not bury uncertainty in the rate. Either clarify it or put it in discovery. Both beat an hourly fog bank. Fog invoices unknown work as “progress.” A list prices known work.